Newcomb Hall First and Fourth Floor Renovation - Week of December 1, 2025

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Continue work on basement MEP rerouting
  • Continue work at transformer pad
  • Continue demo of floors at new elevator shaft
  • Continue steel mobilization
  • Set test for helical piles at transformer pad
  • Recap of week performed (November 22-28)
  • Completed masonry infills at elevator shaft
  • Began gantry crane installation
  • Began floor demo at elevator shaft
  • Completed waterproofing at elevator pit