Paul Hall Clean Room - Week of November 17, 2025

Sources of Noise

  • General Construction activities.
     

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.
  • Flooring materials.

Events for upcoming week

  • Build load platform for Plenum delivery.
  • Coordinate plant removal from bed at clean room north exterior.
  • Remove center window on North clean room wall.
  • Protect window opening.
  • Continue general site cleaning.
  • Receive 1st plenum delivery.

Recap of Week ending November 16, 2025

  • Tie in AHU supply duct to clean room duct.
  • Complete floor level adjustments.
  • Lay flooring in the Clean Room.
  • Send alert for load platform.
  • Lay down protective flooring.
  • End user meeting 13 Nov 2025.
  • Run Sensible chill water lines.
  • Continue to review plenum delivery plan.