TNPRC Cage Run 23- Week of November 17, 2025

Sources of Noise

  • Hand tools.

Utility Shutdowns

  • None.

Deliveries

  • Materials and equipment.

Events for the upcoming week - R 23  

  • Weld additional perches for the two rear enclosures.
  • Continue plumbing gas main.
  • Routing electrical conduits ongoing.
  • Pull electrical and control circuits.
  • Install hardware cloth for high limit sensor protection.
  • Schedule Vet Med and Design Team walk through.


Recap of week ending November 14, 2025 - R 23

  • Mounted penthouse control panel boxes.
  • Routed conduits at the electrical rack.
  • Continued plumbing gas main.
  • Hardware cloth sensor protection mockup approved by Vet Med.
  • Removed existing wall ties and replaced with new wall ties.