Paul Hall Clean Room - Week of November 10, 2025

Sources of Noise

  • General Construction activities

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.
  • Flooring materials.

Events for upcoming week

  • Pressure Test Sensible chill water lines in Penthouse.
  • Continue to adjust floor levels to within specs.
  • Patch around floor drains.
  • Continue installing Sensible Chill water lines to skid location.
  • Continue general site cleaning.

Recap of Week ending November 9, 2025

  • Particulate retest of AHU 5 supply line in clean room 11/3/25. Passed.
  • Install copper and PVC lines for Sensible Chill water skid.
  • Add floor leveling and review tolerances.
  • Grid out floor and mark to verify thicknesses.
  • Continue to review plenum delivery plan.