Sources of Noise
- General Construction activities
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
- Flooring materials.
Events for upcoming week
- Pressure Test Sensible chill water lines in Penthouse.
- Continue to adjust floor levels to within specs.
- Patch around floor drains.
- Continue installing Sensible Chill water lines to skid location.
- Continue general site cleaning.
Recap of Week ending November 9, 2025
- Particulate retest of AHU 5 supply line in clean room 11/3/25. Passed.
- Install copper and PVC lines for Sensible Chill water skid.
- Add floor leveling and review tolerances.
- Grid out floor and mark to verify thicknesses.
- Continue to review plenum delivery plan.