Goldring Tennis and Pickleball Courts - Week of November 10, 2025

Sources of Noise

  • Construction Vehicles.

Utility Shutdowns

  • Future date for water service disruption at U Square and adjacent areas of the neighborhood is pending review.

Deliveries 

  • Construction Materials.
  • Sand/ gravel trucks.
  • Concrete trucks.

Events for the upcoming week

  • Cover area of reconnection for U.S. Army Corps of Engineers (USACE) 10” water line at Leake Ave.
  • Continue curb and flatwork forming and resteel.
  • Continue Grading and compacting subsurface material for Tennis Courts.
  • Grade area around East Tennis fence posts.
  • Form curb along East and West Tennis courts.

Recap of Week ending November 9, 2025

  • Utility connection to USACE South feed identified, located, and connected.
  • Complete Grandstand assembly.
  • Cover 16” ACM to HDPE pipe connection after inspection.
  • Pull scoreboard electrical cables.
  • Complete underground lighting circuit conduit after water utility work areas covered.
  • Form and resteel West Tennis court and North Pickleball curb.
  • Clear area around leaking East 6” valve and Lowerline waterline connection point.
  • Add Sand, geogrid, fabric, and gravel to bring tennis courts to proper grade.