TNPRC Cage Run 23 - Week of November 10, 2025

Sources of Noise

  • Hand tools.
  • Skid Steer.
  • Welding machines.

Utility Shutdowns

  • None currently.

Deliveries

  • None currently.

Events for the upcoming week - R 23  

  • Start plumbing gas main.
  • Continue installing control panels, heater disconnect, and routing conduit.
  • Schedule Vet Med and Design Team walk through.


Recap of week ending November 7, 2025 - R 23

  • Finished wall panels excluding rear side for MEP construction access.
  • Hung support struts and mounted heaters.  
  • Replaced wood perch material throughout the site.
  • Started installing control panels, heater disconnect, and routing conduit.