TNPRC Cage Runs 23 and 26-Week of August 15, 2025

Sources of Noise

-Hand Tools.
-Bobcat.

Utility Shutdowns

-None currently.

Deliveries

-Materials and equipment.

Events for the upcoming week - R 26  

-Finish relocating NHP’s from Run 23 to Run 26.
-Complete labeling.
-Change T-Stat sensor location.
-Begin mobilization to Run 23.

Recap of week ending August 8, 2024 - R 26

-IACUC Walked through and approved NHP’s relocation to Run 26.
-Began relocating NHP’s from Run 23 to completed Run 26.
-Final grading is complete adjacent to Cage Run 26.
-Contractors continued addressing minor punch list items.