Sources of Noise
-Hand Tools.
-Bobcat.
Utility Shutdowns
-None currently.
Deliveries
-Materials and equipment.
Events for the upcoming week - R 26
-Finish relocating NHP’s from Run 23 to Run 26.
-Complete labeling.
-Change T-Stat sensor location.
-Begin mobilization to Run 23.
Recap of week ending August 8, 2024 - R 26
-IACUC Walked through and approved NHP’s relocation to Run 26.
-Began relocating NHP’s from Run 23 to completed Run 26.
-Final grading is complete adjacent to Cage Run 26.
-Contractors continued addressing minor punch list items.