TNPRC JRH1 Phase II - Week of August 15, 2025

Sources of Noise
-Hand tools.
-Welding machines.

Utility Shutdowns

-None Scheduled.

Deliveries

-Materials and equipment.

Events for the upcoming week

-Capital Projects and Kent Construction to pre-punch project.
-Begin removing equipment, materials, and tools.
-Clean debris from site.
-Install catch basin protection plates.
-Install doors, thresholds, and hardware.
-Paint doors.
-Once the punch list is complete, paint floors.

Recap of week ending August 8, 2025

-Completed HDPE enrichment perches.
-Finished gates and detailing panels.
-Welded sliding door rails and latches.
-Sliding aluminum doors onsite.
-Mounted building Pass-throughs to enclosure frames.
-Installed grating over interior tunnels.