Sources of Noise
-Hand tools.
-Welding machines.
Utility Shutdowns
-None Scheduled.
Deliveries
-Materials and equipment.
Events for the upcoming week
-Capital Projects and Kent Construction to pre-punch project.
-Begin removing equipment, materials, and tools.
-Clean debris from site.
-Install catch basin protection plates.
-Install doors, thresholds, and hardware.
-Paint doors.
-Once the punch list is complete, paint floors.
Recap of week ending August 8, 2025
-Completed HDPE enrichment perches.
-Finished gates and detailing panels.
-Welded sliding door rails and latches.
-Sliding aluminum doors onsite.
-Mounted building Pass-throughs to enclosure frames.
-Installed grating over interior tunnels.