TNPRC JRH1 Phase II - Week of August 7, 2025

Sources of Noise

-Hand tools.
-Welding machines.

Utility Shutdowns

-None Scheduled.

Deliveries

-Materials and equipment.

Events for the upcoming week

-Hang gates, mount enrichment perches, and mount Pass-through tunnels.
-Weld lock tabs, latches, gate rails, and hinges throughout the site.

Recap of week ending August 1, 2025

-Completed installing building trim.
-Enrichment perches ongoing.
-Pulled chain fabric, hung gates, and detailed panels.
-Welded latches, gate rails, and hinges throughout the site.