Sources of Noise
-Hand Tools.
Utility Shutdowns
-None at this time.
Deliveries
-Materials and equipment.
Events for the upcoming week - R 26
-Complete the new gas main directional boring.
-Install new CenterPoint gas meter.
-Start the penthouse access panel modifications.
Recap of week ending June 20, 2024 - R 26
-Began directional boring for the new gas main. Completed 1,000 L.F.
-Plumbers tested penthouse heater controls with successful results.
-Work to commence on Cage Run 23 upon completion of Cage Run 26.
-Relocate NHP’s from Cage Run 23 to Cage Run 26 once completed.