TNPRC Cage Runs 23 and 26-Week of June 27, 2025

Sources of Noise

-Hand Tools.

Utility Shutdowns

-None at this time.

Deliveries

-Materials and equipment.

Events for the upcoming week - R 26  

-Complete the new gas main directional boring.
-Install new CenterPoint gas meter.  
-Start the penthouse access panel modifications.

Recap of week ending June 20, 2024 - R 26

-Began directional boring for the new gas main. Completed 1,000 L.F.
-Plumbers tested penthouse heater controls with successful results.
-Work to commence on Cage Run 23 upon completion of Cage Run 26. 
-Relocate NHP’s from Cage Run 23 to Cage Run 26 once completed.