Indoor Practice Facility - Week of April 25, 2025

Sources of Noise

-Heavy equipment

Utility Shutdowns

-None

Deliveries

-Construction trailer

Events for upcoming week

-Form and pour new electrical equipment pad

-Begin grade beam work

-Set up construction trailer

-Reroute of electrical line to new switchgear location

Recap of work performed (April 15 - 21, 2025)

-Lot demolition

-Complete duct bank concrete for new electrical run

-Transformer delivery