Sources of Noise
-N/A
Utility Shutdowns
-None at this time.
Deliveries
-None at this time
Events for upcoming week
-Broadmoor continues field wire item corrections.
-Continue Exterior Emergency Pole installation.
-Change out all air filters and clean ducts in preparation for the IAQ on Feb. 17, 2025.
-3rd week of IAQ test off gassing period.
-No occupants Feb. 14-17 for particulate settling period before IAQ testing.
Recap of Week ending February 9, 2025
-Hang extinguisher in Fire Pump room.
-Continue Field wire item corrections.
-Repaired Cat6 port wiring at 2nd floor punch down. Verified connectivity. Network Services verified that RMH devices are patched in and Wireless is functional.
-Verified with Powers Controls contractor that HVAC network connections are online and functioning.
-Continue paint touch ups and cleaning of paint splatters.
-HVAC system and component training for end users and maintenance staff.
-Plumbing system and component training for end users and maintenance staff.
-Fire pump controller training for end users and maintenance staff.
-Site visit by Event Services and donor relations.
-Complete window 1st floor window membrane application.
-Continue duct detector shut down configuration.
-Continue duct detector cleaning and filter changes.