RMH - Week of August 23, 2024

Sources of Noise

  • Vehicles
  • Dumpsters
  • Tools/ Equipment

Utility Shutdowns

  • None at this time

Deliveries 

  • General construction materials. 
  • Dumpsters

Events for upcoming week

  • Continue East and Northwest exterior drainage installation and repair. 
  • Continue wooden base board installations throughout.
  • Continue VCT installation in 301. Continue carpet installation in 304, prep 404.
  • Continue 5th floor, stair 4, and stair 5 ceiling Tape, Float, and Finish. Homasote board installation continues 4th floor. Paint/ caulk installed Homasote.
  • Continue MEP Trim out on floors 1-4 where painted walls are available.
  • Continue Roof flashing and brick work adjustments.
  • Thompson team inspections continue where available.
  • Continue interior metal storefront installations. Add glass wherever framing it ready.
  • Continue topping slab at interstitial floors. 
  • Install FDC (point of connection at the fire pump room).
  • Prepare front porch for waterproofing.
  • Continue preparations on front porch for surfacing.
  • Continue Fan coil unit testing in classrooms. Prepare for startups.
  • Continue stair 4 and 5 handrail installations.

Recap of Week ending August 18, 2024

  • Move East Fence out to encompass parking spaces along West Road 17Aug2024.
  • Dismantle North load platform scaffolding. Begin removing materials from site.
  • Continue MEP installations throughout.
  • Continue Tape/ Float/ Finish as walls and ceilings become available.
  • Continue duct insulation and fan coil unit wiring/ testing.
  • Add blocking for Zinsell doors.  
  • Fire alarm trim out continues throughout. 
  • Begin removing paint from historic door frames.
  • Dig Southeast ext for Trench drain.
  • Install Loyola gate reader conduit to J-box at South exterior. 
  • Complete VCT installation in room 302, begin room 301.
  • Install partitions in 2nd floor restrooms, layout 3rd floor Women’s room.
  • Caulk and paint interior windows.