Sources of Noise
- Excavator.
- Bobcat.
- Bore machine.
Utility Shutdowns
- None at this time.
Deliveries
- Materials and equipment.
Events for upcoming week
- Continue installing 8” water main from tunnel to water source.
- Continue subsurface boring for new gas main.
- Prep K Field by removing materials, equipment, and tools.
Recap of week ending August 16, 2024
- Trenched, fused, and buried 8” water main from K Field through tunnel.
- Final grade re-established through the tunnel.
- Pre-fused approximately 1,000 LF. of 8” water main stocked in K Field.
- Bored approximately 1,350 LF. of 2” gas main.