TNPRC TUTSI Freezer Project - Week of August 23, 2024

Sources of Noise

  • Hand Tools.
  • Ski Steer.

Utility Shutdowns

  • None at this time.

Deliveries

  • Materials.

Events for upcoming week

  • Install front canopy.
  • Begin routing CO2 Lines throughout building.
  • Professional cleaners are scheduled for Monday.
  • Core door cylinders.
  • Begin painting ceiling drywall.
  • Hydroseed site.
  • Hang lights in Restroom, Electrical, and CO2 Room.
  • Mount Restroom accessories.

Recap of week ending August 16, 2024

  • TBES Pressure tested refrigerant lines.
  • Hung, taped, and skimmed ceiling drywall in CO2 and Electrical Rooms.
  • Pulled control circuit to the existing Freezer Building.
  • Card reader mounted and circuit terminated.
  • Established final grade.
  • Mounted exterior lights.
  • Continued electrical trim out.
  • Metal trim completed.