Sources of Noise
- Hand tools.
- Bobcat.
Utility Shutdowns
- None at this time.
Deliveries
- Materials.
Events for upcoming week
- Move forward framing the building rough openings.
- Create a full mockup of building to exterior tunnel interfacing.
- Complete a working flush system for Vet Med/Architect review.
- Continue the exterior enclosure modifications.
- Mockup exterior cage tunnel for Architects review.
Recap of week ending July 12, 2024
- Vet Med/Architect reviewed squeeze chute mockup.
- Vet Med/Architect approved building rough open framing.
- Began installing metal flashing and termination bar at wall joint.
- Continued HDPE enclosure skirt.
- Moved (2) tunnel frames to accommodate post flanges.
- Started installing flush system plumbing.