Sources of Noise
- Heavy machinery operations.
- Vehicles operations.
- Dumpster activities.
Utility Shutdowns
- None at this time
Deliveries
- Dumpsters
- Construction materials
Events for upcoming week
- Continue new addition Steel fireproofing South. Complete interior steel fireproofing.
- General site cleanup/ safety improvements.
- Continue interior Hangers and wall layouts.
- Continue electrical installation on interior floors. (Rough in)
- Continue 4th floor platform assembly South.
- Continue tuckpointing activities SW and West central exterior. Brick infill at beam pockets East masonry wall.
- Continue Fire lid installation 1st floor existing structure, move to 2nd floor.
- Continue exterior sheathing on new addition. Waterproof sheathing.
- Install plumbing and HVAC pipes/ ducts.
- Continue Historical window installation.
Recap of week ending October 22, 2023
- Continue erection of 4th floor work platform for ceilings.
- Infill brick at east beam pockets South addition. Continue West exterior tuckpointing activities.
- Finish North flat roof, continue Southeast roof repairs, continue NE flashing install.
- Continue plumbing installation throughout building. (Piping and supports.)
- Continue fireproofing South addition.
- Continue interior electrical rough in (lighting and floor boxes).
- Continue HVAC duct work.
- Continue historical window installation.
- Install stair sections and handrails as they arrive.