Richardson Memorial - Week of November 11,2022

Sources of Noise

  • Heavy Equipment operations
  • Auger cast engine, pumps, and drilling
  • Vehicle movement

Utility Shutdowns

  • None at this time

Deliveries 

  • Construction dumpsters
  • General construction materials (supplies, lumber, etc.)
  • Grout trucks for Piles

Events for upcoming week

  • Complete North stair demo/ debris removal
  • Begin pile drilling and grout pouring in NE Site area
  • Layout interior Slab cutting for infrastructure
  • Continue Safety improvements
  • Remove excess dirt from SE site

Recap of week ending Oct 26, 2022

  • North Stair abatement clearance
  • North Stair Demo
  • S Scaffold Stair safety improvements
  • Move West fencing to accommodate Film trucks
  • Relocate west fencing and secure after film crew departure
  • Conducted Architecture tour 11/ 3 and 11/9
  • Reposition crane mats for auger cast drilling