Paul Hall - Week of December 10, 2021

Associated Project

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  •  None   

Deliveries

  • Misc jobsite materials
  • Crane Mats
  • Auger Crane Rig

Events for upcoming week

  • Development of the Paul Hall Project Documents continues
  • Continue load out of debris
  • Root pruning near new sewer line
  • Start interior wall finishing @ building 12
  • Continue Tower Crane electrical feed work
  • Continue site work-grading
  • Continue test piles

Recap of week performed (November 28th-December 4th, 2021)

  • Crane mats delivered
  • Auger pile rig mobilized on site
  • Started layout for Tower Crane electrical feed
  • Repair/reroute sewer
  • Begin tying rebar cages for auger piles
  • Lay out building & column lines