Associated Project
Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Misc jobsite materials
- Crane Mats
- Auger Crane Rig
Events for upcoming week
- Development of the Paul Hall Project Documents continues
- Continue load out of debris
- Root pruning near new sewer line
- Start interior wall finishing @ building 12
- Continue Tower Crane electrical feed work
- Continue site work-grading
- Continue test piles
Recap of week performed (November 28th-December 4th, 2021)
- Crane mats delivered
- Auger pile rig mobilized on site
- Started layout for Tower Crane electrical feed
- Repair/reroute sewer
- Begin tying rebar cages for auger piles
- Lay out building & column lines