Sources of Noise
- Work Vehicles
- Hand Tools
- Power Tools
Utility Shutdowns:
- None
Deliveries
- None
Events for upcoming week
- BNB will perform final touch up paint, final clean, and continue working towards final completion.
- The installation of the q-rail system will continue this week.
- Rocker Electric will continue electrical trim-out.
Recap of week performed (July 14 – July 20, 2019)
- BNB is monitoring the completion of q-rail handrail system. Other activities in progress are touch up paint, ceiling tile installation, carpet installation, and final clean.
- Rocker Electric continues electrical trim-out.
- Venable Terrazzo completed the terrazzo patch work.