Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of March 4, 2018
Sources of Noise
Hand Tools
Power Tools
Material Delivery
Equipment
Hand Tools
Power Tools
Utility Shutdowns
The contractor has notified the team that work associated with the electrical work may temporarily disrupt power to certain circuits within Provost Suite area on 03/07/2018.
Deliveries
None
Events for upcoming week
BNB will continue interior painting.
Rocker Electric has requested that work associated with the replacement of the branch circuit receptacles occur on 03/07/2018, at 6AM.
Tulane Networking will replace the existing data and communication box faceplates.
Recap of work performed (February 28 – March 3, 2018)
The Contractor, BNB, has completed Phase 3 of the Provost Suite Renovation.
BNB reinstalled the end user’s furniture in Phase 3, after the work was completed.
A pre-construction conference was held on 2/30/2018, in preparation of the work starting in phase 4.
The Contractor has removed the furniture from within Phase 4, and commenced prepping the walls for paint, and carpet removal.