Indoor Practice Facility - week of October 27, 2025

Sources of Noise

-Heavy equipment

Utility Shutdowns

-None

Deliveries

-None

Events for upcoming week

-Continue dome installation

-Continue electrical panel work 

-Form and pour light pole bases and curbing

-IT closet floor work, HVAC and electrical trim out


Recap of work performed (Oct 21 - 27, 2025)

-Roll out building panels, assemble and anchor to the grade beam

-Continue panel build

-IT closet work

-HVAC duct work

-Complete fiber optic conduit at Yulman, pour new concrete pad