Hutchinson Memorial Building Renovation L7 - Week of June 27, 2025

Sources of Noise
-Power tools: grinders, Hammer drills, chipping guns, etc...


Utility Shutdowns
-Electrical 6-17-2025/6-18-2025


Deliveries
-Random


Events for upcoming week

-Ceramic Tile Installation Zone G
-Final Paint Zone B
-Install Doors and Misc. Accessories Zone B
-Millwork & Casework Installation Zone B
-Ceiling Trim Outs Zone G
-Install Door and Misc. Acessories
-Final MEP Connections


Recap of work performed (June 16-21, 2025)


-Ceiling Tile installation Zone G
-Tape, Float, Bed and Prime Walls Zone G
-Lab Case work Installation Zone D
-Ceiling Trim Outs Zone G
-Install Doors and Misc Accessories Zone B, D
-Final Paint Zone B (Slipping)