Housing Phase II - Week of November 10, 2023

Associated Project

Sources of Noise

  • Power tools
  • Chipping Hammer
  • Trucks 
  • Machines

Utility Shutdowns w/ excavation to begin:

  • Water:  
  • Power: 
  • Chilled 

 
Deliveries

  • N/A

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • N/A

Events for upcoming week

  • Forming and pouring pile caps
  • Installing drainpipes
  • Installing Tower Crane


Recap of week ending November 1, 2023

  • Installing Tower Crane
  • Pouring piles
  • Forming and pouring pile cap