Housing Phase II - Week of June 27, 2025

Sources of Noise
-Power tools
-Chipping Hammer
-Trucks 
-Machines


Utility Shutdowns w/ excavation to begin:
-Water:  
-Power: 
-Chilled 

Deliveries
-N/A

Road Closures/Blockages
-N/A

Approved Extended Work Hours
-7 a.m. to 6 p.m. M-F
-8 a.m. to 6 p.m. S+S

Events for upcoming week
-Forming and pouring sidewalks
-Working on Brick
-Painting and Flooring
-Deliveries


Recap of week ending June 21, 2025
-Forming and pouring sidewalks
-Working on Brick
-Planting plants
-Painting and Flooring
-Deliveries