Greenwave Indoor Practice Facility - Week of December 15, 2025

Sources of Noise

  • Heavy equipment
     

Utility Shutdowns

  • None


Deliveries

  • None

 

Events for upcoming week

  • Complete dome insulation
  • Curb forming
  • Electrical trim out
  • Data trim out


Recap of work performed (Dec 9 - 15, 2025)

  • Continue dome insulation
  • Continue electrical trim out
  • Complete installation of anchor points for hanging equipment
  • Continue work on Trane units
  • Pull wire to IT closet