Goldring Tennis and Pickleball Courts - Week of October 27, 2025

Associated Project

Sources of Noise

  • Construction Vehicles.

Utility Shutdowns

  • Future date for water service disruption at U Square and adjacent areas of the neighborhood is pending review.

Deliveries 

  • Construction Materials.
  • Sand/ gravel trucks.
  • Concrete trucks.

Events for the upcoming week

  • Flowable fill abandoned underground pipes.
  • Review and reschedule follow up water service shut down.
  • Pour curbs at NW tennis parking lot and North Pickleball court.
  • Add pull strings to conduits.
  • Set Tennis Net foundations with Soni tube and resteel.
  • Rebuild underground vault wall at the backflow preventer location.
  • Inspect waterline tie in locations.
  • Rough in wire pathway through suite 108.
  • Review corrective measures for leaking underground lead bell pipe connection.

Recap of Week ending October 26, 2025

  • Utility shutdown of water services that run through university square.
  • Shutdown recap meeting Sunday afternoon.
  • Continue to add sand to Tennis court area and bring base up. Compact.
  • Continue Scoreboard electrical prep.
  • Flush HDPE water pipes.
  • Clear pickleball net foundation pole openings.
  • Add rock behind North chain wall to bring up grade.
  • Pave grandstand sidewalk.
  • Trim pickleball asphalt edge on North side.
  • Prep site for Saturday water line tie ins.
  • Add resteel to Northeast tennis and North pickleball curbing.