Associated Project
Sources of Noise
- Construction Vehicles.
Utility Shutdowns
- Future date for water service disruption at U Square and adjacent areas of the neighborhood is pending review.
Deliveries
- Construction Materials.
- Sand/ gravel trucks.
- Concrete trucks.
Events for the upcoming week
- Flowable fill abandoned underground pipes.
- Review and reschedule follow up water service shut down.
- Pour curbs at NW tennis parking lot and North Pickleball court.
- Add pull strings to conduits.
- Set Tennis Net foundations with Soni tube and resteel.
- Rebuild underground vault wall at the backflow preventer location.
- Inspect waterline tie in locations.
- Rough in wire pathway through suite 108.
- Review corrective measures for leaking underground lead bell pipe connection.
Recap of Week ending October 26, 2025
- Utility shutdown of water services that run through university square.
- Shutdown recap meeting Sunday afternoon.
- Continue to add sand to Tennis court area and bring base up. Compact.
- Continue Scoreboard electrical prep.
- Flush HDPE water pipes.
- Clear pickleball net foundation pole openings.
- Add rock behind North chain wall to bring up grade.
- Pave grandstand sidewalk.
- Trim pickleball asphalt edge on North side.
- Prep site for Saturday water line tie ins.
- Add resteel to Northeast tennis and North pickleball curbing.