Associated Project
Sources of Noise
- Construction Vehicles.
Utility Shutdowns
- Water service disruption at U Square rescheduled for 26 Oct 2025.
Deliveries
- Construction Materials.
- Sand/gravel trucks.
Events for the upcoming week
- Continue Tennis court grading.
- Saw cut pickleball court East edge and expose court net post bases.
- Continue electrical pathways for power and technology infrastructure.
- Flush 16” HDPE pipe.
- Form fence footings around transformer pad.
- Continue prep backflow preventer installation.
- Tie in 16” water line to existing main 26 Oct 2025.
Recap of Week ending October 19, 2025
- Remove spoils.
- Add sand to Tennis court area and bring base up.
- Continue Scoreboard electrical prep.
- Chlorinate and flush 16” HDPE pipe.
- Donahoe mobilized on 13 oct 2025. Demobilized on 17 oct 2025.
- Pave drive lane base layer.
- Pave pickleball surfacing.
- Continue grading area North of tennis court chain wall.
- Add sand to area south of grandstand, north of drive lane curb.
- Prep backflow preventer connection pipes.