Goldring Tennis and Pickleball Courts - Week of October 20, 2025

Associated Project

Sources of Noise

  • Construction Vehicles.

Utility Shutdowns

  • Water service disruption at U Square rescheduled for 26 Oct 2025.

Deliveries 

  • Construction Materials.
  • Sand/gravel trucks.

Events for the upcoming week

  • Continue Tennis court grading.
  • Saw cut pickleball court East edge and expose court net post bases.
  • Continue electrical pathways for power and technology infrastructure.
  • Flush 16” HDPE pipe.
  • Form fence footings around transformer pad.
  • Continue prep backflow preventer installation.
  • Tie in 16” water line to existing main 26 Oct 2025.

Recap of Week ending October 19, 2025

  • Remove spoils.
  • Add sand to Tennis court area and bring base up.
  • Continue Scoreboard electrical prep.
  • Chlorinate and flush 16” HDPE pipe.
  • Donahoe mobilized on 13 oct 2025. Demobilized on 17 oct 2025.
  • Pave drive lane base layer.
  • Pave pickleball surfacing.
  • Continue grading area North of tennis court chain wall.
  • Add sand to area south of grandstand, north of drive lane curb.
  • Prep backflow preventer connection pipes.