Sources of Noise
- Construction Vehicles.
Utility Shutdowns
- Future date for water service disruption at U Square and adjacent areas of the neighborhood is pending review.
Deliveries
- Construction Materials.
- Sand/ gravel trucks.
- Concrete trucks.
Events for the upcoming week
- Cover area of reconnection for U.S. Army Corps of Engineers (USACE) 10” water line at Leake Ave.
- Continue curb and flatwork forming and resteel.
- Continue Grading and compacting subsurface material for Tennis Courts.
- Grade area around East Tennis fence posts.
- Form curb along East and West Tennis courts.
Recap of Week ending November 9, 2025
- Utility connection to USACE South feed identified, located, and connected.
- Complete Grandstand assembly.
- Cover 16” ACM to HDPE pipe connection after inspection.
- Pull scoreboard electrical cables.
- Complete underground lighting circuit conduit after water utility work areas covered.
- Form and resteel West Tennis court and North Pickleball curb.
- Clear area around leaking East 6” valve and Lowerline waterline connection point.
- Add Sand, geogrid, fabric, and gravel to bring tennis courts to proper grade.