Goldring Tennis and Pickleball Court - Week of November 17, 2025

Sources of Noise

  • Construction Vehicles

 

Utility Shutdowns

  • Water service disruption at Lowerline St. and adjacent areas of the neighborhood November 20, 2025.

 

Deliveries 

  • Construction Materials.
  • Concrete trucks.

 

Events for the upcoming week

  • Form West tennis sidewalk and add resteel.
  • Complete wall pack light mounting on University Square building.
  • Pour concrete for flatwork.
  • Lowerline street water shutdown scheduled for 20 November 2025 for 8” tie in.
  • Add conduit for Grandstand power and data.
  • Cut expansion joints in newly poured flatwork and finish surfaces.
  • General site cleanup.

 

Recap of Week ending November 16, 2025

  • Complete mounting of exterior lot lights on the poles.
  • Demo flatwork at grandstand to correct grading.
  • Review waterline shutdown scenarios. Coordinate with SWBNO and Cycle construction.
  • Distribute water service disruption notices to neighborhood and alert to university.
  • Continue grading and compaction of Tennis subsurface material.
  • Pour flatwork at backflow preventer, north grandstand overhang, NW tennis flagpole area, and North Pickleball court.
  • Anchor lighting to University square building outside of the TUPD suite and the old theater.  
  • Repair Cox cable run at East tennis fenceline.
  • Walk through site with TruConnect and Tech Infrastructure Project rep.
  • Add black vinyl fencing to pickleball courts.
  • Remove forms and finish curbing at SW tennis, NW Tennis, East grandstand, and North Pickleball court.