Associated Project
Sources of Noise
- None
Utility Shutdowns w/ excavation to begin:
- Deliveries
- Miscellaneous Deliveries
Road Closures/Blockages
- N/A
Approved Extended Work Hours
- Sat. 8am to 5pm
- Sun. 9am to 5pm
Events for upcoming week
- Continue site work
- Continue Test and Balance of HVAC
- Continue installation of raised subfloor and slate tile at 3rd floor
- Fire alarm testing
- Continue Final Paint on 1st and 2nd floors
- Make final connections to kitchen equipment
- Install ceiling tiles
- Commission Hoods @ 1st floor
Recap of week ending June 29, 2019
- Continue terrazzo flooring
- Continue with interior Glass walls
- Continue to hang doors
- Continue with Cw & Glass Installation
- Continue installation of Glass handrails
- Continue programing and testing lights
- Continue final paint on 1st, 2nd, and 3rd floors
- Continue site work