College Track LaSalle Garage - Week of October 27, 2025

Sources of Noise

  • Power tools: grinders, Hammer drills, chipping guns, etc...

Utility Shutdowns

  • Sprinkler shutdown scheduled for 10/20/25 to remove hose box


Deliveries

  • None

Events for the upcoming work week

  • ENFRA laying out and starting to rough in on the mezz
  • Marvin starting in wall rough in on the mezz
  • King framing on the mezz
  • QC coming back onsite to clean up hangers and track that was left on deck


Recap of work performed (Oct 20-24, 2025)

  • Jefferson Sprinkler removed fire hose box from stairwell on 1st floor
  • King started framing on the mezz
  • ENFRA laying out and started roughins on the mezz
  • Marvin starting rough ins on the mezz
  • NOIW removed the old air handlers