Weinmann Roof Repair - Week of June 14, 2024

Sources of Noise

- Angle grinders and hand tools


Utility Shutdowns

- AHU-1 shutdown on Thursday, 6/13


Deliveries

- New motor for AHU-1 return air fan


Events for upcoming week

- Crane lift on Thursday, 6/13
- Roof demolition and reinstallation in the AHU-5 mechanical yard
- SS parapet cap installation
- Commissioning work on AHU-2 and AHU-5


Recap of work performed (June 4 -10, 2024)

- Site visit/testing with waterproofing consultant
- Start roof deck work in mechanical yard 5
- SS parapet cap installation
- Waterproofing coating applied to center roof and west roof walls
- Commissioning of AHU-2 & AHU-5