Sources of Noise
- Angle grinders and hand tools
Utility Shutdowns:
- None
Deliveries
- None
Events for upcoming week
- Move scaffolding from Monroe side to Freret side of building
- Build scaffolding at the main entrance to support the swing stage
- Penthouse apron detail work
- Sealing and PMMA work in Mechanical Yard 2
- Sealing and PMMA work in Mechanical Yard 5
Recap of work performed (Aug 13 - 19, 2024)
- Top layer of roofing material (white cap) on center tower complete
- North wall sealed, gutter work complete
- Gutter work on north wall
- Sealant and PMMA work in Mechanical Yard 2