The Sewerage and Water Board of New Orleans will conduct paving work in the areas listed below. Access in the area will generally be maintained during the project. However, certain construction activities may require temporary lane restrictions. Please allow extra time when traveling through  work zones.

Thursday, March 19

Calhoun Street at Willow Street

  • Saw cutting and road removal.

Audubon Boulevard to Broadway Street, along Willow Street

  • Saw cutting and removal of roadway, including curb areas.

Friday, March 20

Calhoun Street at Willow Street

  • Asphalt paving.
  • Willow Street from Ben Weiner to Calhoun will be closed.

Audubon Boulevard at Willow Street

  • Road reconstruction.

Monday, March 23

Audubon Boulevard at Willow Street

  • Asphalt paving.

Ben Weiner Drive by TISM

  • Asphalt overlay and repairs.

Please plan ahead and expect delays.