TNPRC Building 2 - Week of January 24, 2020

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Continue casework MEP connections.
  • Install supply and exhaust grilles.
  • Hang doors and install hardware.  
  • Test electrical devices, trim out, pull circuits, and hang new lights.
  • Caulk glazing and install rubber seal on exterior glass system.
  • Continue applying finishes.  

Recap of week ending January 23, 2019

  • Demolished AHU3 and duct.  Prepped and Poured concrete in penetration.
  • Energized new panels and lights, removed temporary electrical service, pulled circuits, provided power to casework, and continued hanging lights.
  • Continued interior door and hardware installation.    
  • Began leveling subfloor and install floor system. 
  • Drywall and frame finish ongoing.  
  • Completed courtyard exterior glazing.  ACM panels at 90%.  
  • Casework plumbing tie in.  Rerouted existing chill and steam lines.