Sources of Noise

  • Excavation equipment.
  • Hand Tools.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Form and pour concrete mow strip for field enclosure two.
  • Continue to pull and tie chain fence at field enclosure two.
  • Haul and spread topsoil inside of field enclosure two.
  • Water installation at field enclosure one moving forward.
  • Weld rails and post on field enclosure two ongoing.
  • Tack weld horizonal rails at enclosure one.
  • Continue electrical rough in and rack installation.

Recap of week ending November 4, 2021

  • Hauling and spreading topsoil in field enclosure two ongoing.
  • Continued pulling vertical fencing at field enclosure two.
  • Road swale minor adjustments progressing.
  • Completed trenching for lixits at field enclosure one.