Richardson Hall - Week of October 2, 2020

Possible Sources of Noise

  • Tools
    • Saws
    • Grinders
    • Compressors
    • Nail Guns
    • Hammering
    • Fans
    • General jobsite noise
  • Delivery Trucks

Utility Shutdowns

  • None Scheduled

Deliveries/Pick-up

  • Framing materials
  • Misc job materials

Events for upcoming week

  • Contractor to begin concrete work @ rear ADA ramp & stairs
  • Continue structural work on 3rd floor
  • Contractor to continue electrical rough in
  • Contractor to begin mechanical work @ auditorium ceiling
  • Contractor to continue

Weekend Work (Sat October 3, 2020)

  • None

Recap of week ending (October 3, 2020)

  • Contractor completed CMU block @ rear stairs ADA ramp
  • Contractor began sheetrock @ 2nd floor corridor
  • Continued misc sheetrock
  • Continued electrical rough in
  • Continued installing floor boxes
  • Continued structural/steel work on 3rd floor
  • Contractor began CMU block walls @ elevator shaft
  • Contractor filled CMU block cells @ exterior stairs
  • Continued pulling new data wire
  • Continued sanding & priming on 1st & 2nd floor
  • Completed demo of footings @ elevator pit