Possible Sources of Noise
- Tools
- Saws
- Grinders
- Compressors
- Nail Guns
- Hammering
- Fans
- General jobsite noise
- Delivery Trucks
Utility Shutdowns
- None Scheduled
Deliveries/Pick-up
- Framing materials
- Misc job materials
Events for upcoming week
- Contractor to begin concrete work @ rear ADA ramp & stairs
- Continue structural work on 3rd floor
- Contractor to continue electrical rough in
- Contractor to begin mechanical work @ auditorium ceiling
- Contractor to continue
Weekend Work (Sat October 3, 2020)
- None
Recap of week ending (October 3, 2020)
- Contractor completed CMU block @ rear stairs ADA ramp
- Contractor began sheetrock @ 2nd floor corridor
- Continued misc sheetrock
- Continued electrical rough in
- Continued installing floor boxes
- Continued structural/steel work on 3rd floor
- Contractor began CMU block walls @ elevator shaft
- Contractor filled CMU block cells @ exterior stairs
- Continued pulling new data wire
- Continued sanding & priming on 1st & 2nd floor
- Completed demo of footings @ elevator pit