Richardson Hall 1st Floor Renovation- Week of November 1, 2019

Possible Sources of Noise

  • Tools

    • Saws
    • Grinders
    • Compressors
    • Nail Guns
    • Hammering
    • Fans
    • General jobsite noise
  • Delivery Trucks

Utility Shutdowns

  • None Scheduled

Shutdowns

  • None

Deliveries/Pick-up

  • Framing materials
  • Plumbing Materials
  • Electrical Materials

Events for upcoming week

  • Plumbers to continue crawlspace work & rough in
  • Electricians to continue rough in 
  • Mechanical sub to continue duct install

Weekend Work (Sat-Sun November 2-3, 2019)

  • None

Recap of week ending (November 2, 2019)

  • Contractor completed new steel column & beam install
  • Plumbers continued work in crawlspace
  • Electricians continued rough in & began crawlspace work
  • Contractor continued misc jobsite cleanup