Richardson Hall 1st Floor Renovation- Week of April 19, 2019

Possible Sources of Noise

  • Delivery Trucks
  • Contractor Trucks
  • Small Power Tools (Drills, saws etc.) 
  • Manual Tools (Hammers, pry bars, sledgehammer, etc.) 

Utility Shutdowns

  • None

Shutdowns

  • Toilet Rooms – Women’s Toilet Room ONLY will come off line Monday April 22, 2019. Portable toilets will be available at the North side of Richardson. A gender neutral toilet room is available on the 2nd floor of Richardson. Toilet rooms are also availible on the first floor of adjacent buildings, Stanley Thomas and Richardson Memorial. 
  • Bike Racks have been relocated directly across sidewalk

Deliveries/Pick-up

  • Misc Equipment 
  • Removal of demo debris (trailers will occupy parking spaces) 

Events for upcoming week

  • Contractor to continue demo on interior walls & framing
  • Contractor to continue removing existing mechanical connections
  • Contractor to begin demo of Women’s toilet room

Weekend Work ( Sat-Sun April 20-21 , 2019)

  • None

Recap of week ending (April 20, 2019)

  • Contractor continued 1st floor exploratory demo (quad side)
  • Contractor began demo of interior walls & framing (quad and Engineers Rd side) 
  • Contractor began removing misc existing mechanical conditions
  • Contractor finished cut/cap at mechanical systems. 
  • Contractor completed heating hot water and chilled water shutdown on Tuesday April 16th.