Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Job trailers
- Misc jobsite materials
- Misc equipment
Events for upcoming week
- Development of the Paul Hall Project Documents continues
- Continue form work @ podium
- Underground work @ Flower Hall entrance to continue
- Continue forming & pouring columns
- Begin in slab rough in for podium pour
- 1st Podium pour 6/3
Recap of week performed (May 23rd – May 28th 2022)
- Start water & storm drain work @ Flower Hall Entrance
- Started forming up podium
- Continued underground work
- Continued rebar & formwork for columns
- Continued site work