Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of March 4, 2018
Sources of Noise
- Hand Tools
- Power Tools
- Material Delivery
Equipment
Utility Shutdowns
- The contractor has notified the team that work associated with the electrical work may temporarily disrupt power to certain circuits within Provost Suite area on 03/07/2018.
Deliveries
Events for upcoming week
- BNB will continue interior painting.
- Rocker Electric has requested that work associated with the replacement of the branch circuit receptacles occur on 03/07/2018, at 6AM.
- Tulane Networking will replace the existing data and communication box faceplates.
Recap of work performed (February 28 – March 3, 2018)
- The Contractor, BNB, has completed Phase 3 of the Provost Suite Renovation.
- BNB reinstalled the end user’s furniture in Phase 3, after the work was completed.
- A pre-construction conference was held on 2/30/2018, in preparation of the work starting in phase 4.
- The Contractor has removed the furniture from within Phase 4, and commenced prepping the walls for paint, and carpet removal.