Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of February 4, 2018
Sources of Noise
- Hand Tools
- Power Tools
- Material Delivery
Equipment
Utility Shutdowns
- Electric disruption may occur this week.
Deliveries
Events for upcoming week
- BNB will reinstall the furniture in the offices within Phase 2. Once complete, the Contractor will commence work in the conference room.
- Rocker Electric will return to replace the remainder of the switches and receptacles.
- O’Brian Flooring is scheduled to install carpet.
Recap of work performed (January 28 – February 01, 2018)
- The Contractor, BNB, started work on Phase 2 of the Provost Suite Renovation project.
- BNB began prepping and painting the walls, doors, and trim.
- BNB commenced removing the existing carpet.
- Rocker Electric replaced 50% of the switches and receptacles.