Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of February 4, 2018

Sources of Noise

  • Hand Tools
  • Power Tools
  • Material Delivery

Equipment

  • Hand Tools
  • Power Tools

Utility Shutdowns

  • Electric disruption may occur this week. 

Deliveries

  • Carpet

Events for upcoming week

  • BNB will reinstall the furniture in the offices within Phase 2. Once complete, the Contractor will commence work in the conference room.
  • Rocker Electric will return to replace the remainder of the switches and receptacles. 
  • O’Brian Flooring is scheduled to install carpet.

Recap of work performed (January 28 – February 01, 2018) 

  • The Contractor, BNB, started work on Phase 2 of the Provost Suite Renovation project.
  • BNB began prepping and painting the walls, doors, and trim. 
  • BNB commenced removing the existing carpet.
  • Rocker Electric replaced 50% of the switches and receptacles.