Sources of Noise
-Vehicles
Utility Shutdowns
-None at this time.
Deliveries
-Construction Materials
Events for the upcoming week
-Monitor River level. Work pending Army Corps of Engineers approval.
-11.8ft on 9 June 25
-Continue site prep/ layout.
Recap of Week ending June 5, 2025
-Observe site conditions… All clear.
-Relayed Drone information to Cycle construction.
-Power on Perrier st poles redirected away from University Square by Entergy.
-Power removed from remaining power poles. They were cut down to the AT&T/ Cox level.
-Checked water leaks in utility easement. S&WB meter leak.