Associated Project
Sources of Noise
- Heavy construction equipment.
- Dump Trucks.
- Demo activity.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
Events for upcoming week
- Continue grow period for Newcomb Quad (NQ).
- Air spade water line relocation area North Central Plaza zone.
- Air spade central bench installation areas in Central Plaza zone.
- Begin gravel removal from plaza zone.
- Continue Plaza/ garden drainage.
- Grade area of West Berger Family Lawn (BFL) steam repair.
Recap of Week ending September 27, 2025
- Complete NQ sod installation.
- Begin grow period.
- Continue Newcomb place surfacing demo.
- Remove Debris.
- Complete West BFL steam insulation repairs (24 Sept 26).
- Backfill steam repair excavation.
- Review Airspade areas with Bayou Tree and SEF.
- Review French Drain area with SEF.