Associated Project
Sources of Noise
- Heavy construction equipment.
- Dump Trucks.
- Demo activity.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
- Sod for Newcomb Quad (NQ)
Events for upcoming week
- Continue NQ Sod installation.
- Continue Newcomb place surface asphalt demo.
- Continue grading NQ.
- Continue Plaza/ garden drainage.
- Continue steam insulation repairs West Berger Family Lawn (BFL).
- Layout central lighting. Review for conflicts.
Recap of Week ending September 20, 2025
- Complete NQ irrigation lines to center boundary. Wire in controller.
- Reassemble benches at Dixon curve. Remove crushed granite at tree base.
- Continue Newcomb place surfacing demo.
- Remove Debris.
- Continue West BFL steam insulation repairs.
- Add garden inlet extensions in Plaza/ garden zone.
- Continue NQ Sod installation.
- Pour and backfill drain line at West NQ.
- Review irrigation issues with Facilities and Mullins.
- Meet with SWBNO 9/18 to discuss water line relocation and sewer tie in requirements.
- Add sand to fill gaps on BFL.