Unified Green - Week of September 21, 2026

Associated Project

Sources of Noise

  • Heavy construction equipment.
  • Dump Trucks.
  • Demo activity.

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.
  • Sod for Newcomb Quad (NQ)

Events for upcoming week

  • Continue NQ Sod installation.
  • Continue Newcomb place surface asphalt demo.
  • Continue grading NQ.
  • Continue Plaza/ garden drainage.
  • Continue steam insulation repairs West Berger Family Lawn (BFL).
  • Layout central lighting. Review for conflicts.

Recap of Week ending September 20, 2025

  • Complete NQ irrigation lines to center boundary. Wire in controller.
  • Reassemble benches at Dixon curve. Remove crushed granite at tree base.
  • Continue Newcomb place surfacing demo.
  • Remove Debris.
  • Continue West BFL steam insulation repairs.
  • Add garden inlet extensions in Plaza/ garden zone.
  • Continue NQ Sod installation.
  • Pour and backfill drain line at West NQ.
  • Review irrigation issues with Facilities and Mullins.
  • Meet with SWBNO 9/18 to discuss water line relocation and sewer tie in requirements.
  • Add sand to fill gaps on BFL.