Associated Project
Sources of Noise
- Heavy construction equipment.
- Demo activity.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
- Sod for Newcomb Quad
Events for upcoming week
- Continue Newcomb Quad irrigation installation.
- Continue Newcomb place surface asphalt demo.
- Continue consolidate job site materials.
- Continue grading Newcomb Quad.
- Begin sod on Newcomb Quad.
- Continue Plaza/ garden drainage.
- Continue steam insulation repairs West BFL.
- Continue air spade central seating base area for root conflicts.
Recap of Week ending September 13, 2025
- Complete Newcomb Quad irrigation lines to center boundary.
- Begin Newcomb Quad irrigation install.Continue Newcomb place surfacing demo cleanup.
- Remove Debris.
- Continue West BFL steam insulation repairs.
- Backfill 1st steam expansion loop area.
- Layout seating installations in Plaza/ garden zone.
- Consolidate site materials.
- Install drain at South Benson Plaza stair.
- Run irrigation control wire to existing control location.
- Additional grass cutting on BFL.
- Add sand to fill gaps on BFL.