Sources of Noise

  • Heavy construction equipment.
  • Dump Trucks.

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.

Events for upcoming week

  • Continue grow period for Newcomb Quad (NQ).
  • Continue 8” water main relocation activity.
  • Continue air spade in plaza root conflict zones.
  • Continue Plaza/ garden drainage.
  • Continue Fine tune NQ grading.
  • Drop North NQ drain inlet 1”- 2”.
  • Relocate surplus fence poles off site.

Recap of Week ending October 18, 2025

  • Review Airspade needs and schedule Bayou Tree.
  • Continue NQ grow period.
  • Continue Newcomb place drainage work in plaza zone.
  • Remove Debris.
  • Receive sand.
  • Reset scrim.