Associated Project
Sources of Noise
- Heavy construction equipment.
- Dump Trucks
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
Events for upcoming week
- Continue grow period for Newcomb Quad (NQ).
- Meet on site with Arborist.
- Continue 8” water main relocation activity.
- Continue gravel removal from plaza zone.
- Continue Plaza/ garden drainage.
- Fine tune NQ grading.
- Drop North NQ drain inlet 1”- 2”.
- Relocate surplus fencing off site.
Recap of Week ending October 11, 2025
- Walk NQ with Mullins, SEF, TU grounds, and TU Capital Projects to look at the lawn condition and any punch list items.
- Meet on site with Towers Golde, SEF, Bayou Tree, Tulane Capital Projects to discuss tree root conflicts at central seating.
- TU Capital Projects met TU planning on site to discuss project concerns.
- Hurricane prep.
- Continue NQ grow period.
- Continue Newcomb place drainage work in plaza zone.
- Organize site storage to clear central work zones.
- Remove Debris.
- Receive sand.
- Construct brick manholes at North central garden drains. Backfill the area.