Associated Project
Sources of Noise
- Heavy construction equipment.
Utility Shutdowns
- None at this time.
Deliveries
- Rock and Sand.
- General construction materials.
Events for upcoming week
- Set Drainage in/outflow boxes on Newcomb Quad.
- Complete Drainage tie in on BFL.
- Complete covering Berger Family Lawn (BFL) with native soil layer.
- Continue Rock Fill grading on Newcomb Quad excavation.
- Continue drainage installation on Newcomb quad.
- Air spade utility route areas in coordination with Bayou Tree.
- Mullins Mobilization for BFL sprinkler and sod activities.
- Begin BFL surface prep for sprinkler system and sod.
- Prepare for Newcomb circle paving/ drainage activities.
Recap of Week ending June 21, 2025
- Complete BFL In/ Out box installations.
- Remove sump pump lines from BFL manhole.
- Repair Srim from wind damage.
- Newcomb Quad SE outlet transition box set in place and covered.
- Receive Newcomb Quad ADS system components.
- Reposition materials on Newcomb Quad to clear BFL.
- Complete ADS system arch placements.
- Connect SE and SW transition boxes.
- Continue Rock fill on Newcomb Quad. Begin grading.
- Continue Air spade around drainage boxes and utility routes near trees on Newcomb quad.
- Meet with Mullins and grounds to discuss sod and sprinkler installation.